There will be a public hearing on February 27, 2023 at 11:00 am at the DEQ offices in Woodbridge, VA. It will be in the Conference Room of the DEQ Northern Regional Office at: 13901 Crown Court, Woodbridge VA, at 11:00 a.m. The meeting is to discuss and hear comments on the proposal to allow datacenters in Northern Virginia to operate during times of constrained power on their thousands upon thousands of backup generators. The generators are stationary sources of air pollution equivalent to thousands of heavy duty diesel trucks running in our backyard. This could be a critical public health issue for many and should be treated as such.
Loudoun County has courted data and cloud companies making development and land use decisions that has resulted in Loudoun County having the highest concentration of data centers in the world. These data centers provide a very significant amount of revenue to the county through real estate and business personal property taxes. In recent years, Prince William County has copied Loudoun County’s approach and approved many data centers. Data center growth in Prince William County has increased significantly and is poised to take off.
However, data center operation relies on the use of large amounts of
electricity from the grid. Dominion Energy has informed Loudoun County that it
will not be able to provide power to new data center projects in Ashburn at
this time. They lack adequate transmission capacity and building it
could delay new data centers coming online by a year or more. Virginia is concerned
that the Counties of Fairfax, Loudoun, and Prince William may not have
sufficient electricity for data centers in the next couple of years due to
severe, localized constraints in electricity transmission. Dominion has
already informed the counties that a transmission constraint exists in the area
which may affect the ability to provide enough electricity to data centers
through 2025. In particular, the period between March and July 2023 has
been identified as a time of potentially acute stress on the transmission
capacity of the grid.
Now, the VA Department of Environmental Quality (DEQ) has issued a notice of action that would authorize the data centers' on-site generators to operate during times that fall short of a PJM declared emergency but when transmission constraints and strain on the electric grid would be acute and thereby allow the data centers to continue to operate instead of shutting down to alleviate demand on the electric grid. While Dominion can buy electricity from the PJM members (Pennsylvania and West Virginia who generate electricity by natural gas and coal) there is simply inadequate transmission lines to meet all the demand in Loudoun, Prince William and Fairfax at this time. So, they are going to produce the needed electricity in the dirtiest way possible.
According to the California Air Resources Board: “Standard gasoline
and diesel generators emit a lot more pollutants and greenhouse gas than some
other options…Diesel particulate matter (PM) emissions from an average
industrial diesel generator (~800 hp), operating at an average load of ~300 kW
for 1 hour, is equivalent to driving nearly 660 miles in an average heavy duty
diesel truck.” Each data center has 250-300 diesel generators. What the DEQ is proposing is to have the equivalent of thousands of heavy duty diesel trucks running (not idling) in one spot in our counties for hours or possibly days.
Health effects can result from both short-term and long-term
exposure to particulate pollution. People most sensitive to particulate
pollution include infants and children, the elderly, and people with existing
heart and lung disease. The smallest particles can penetrate deepest, causing
the greatest harm. Particles created from
combustion soot tend to be fine particles with diameters smaller than 2.5
microns (PM 2.5) which are the most dangerous because it lodges in the lungs.
The U.S. Environmental Protection Agency, EPA, requires states to monitor air pollution to assess air quality and ensure that they meet minimum air quality standards. The US EPA has established both annual and 24-hour PM2.5 air quality standards (as well as standards for other pollutants). The annual standard established in 2012 is 12 µg/m³ (an AQI of 39). The 24-hr standard remained at 35 µg/m³ (an AQI of 99). Exceeding the 24 hour standard could cause acute health impacts. In addition, there are other air quality rules that might come into play here specifically the Clean Air Non-Road Diesel Rule of 2004.
In 2020 electricity used in Virginia in 2020 was 30% more than the electricity used in 2010. The one growing sector of electricity demand in Virginia is data centers. In 2018 power demand for data centers was just over 1 gigawatt of power, by 2022 that had reached 2 gigawatt of power and is projected to reach 3 gigawatts by 2025 with projects already under way. The current power usage by data centers is more than to the power usage of 1.5 million houses which is almost half of all Virginia households.
Virginia is the data
center capital of the world resulting in electricity use
growing faster here than other states. Now the DEQ is proposing to turn us at least sporadically into the air pollution capital. Governor Youngkin has just trumpeted and
praised the announcement from Amazon that they plan to invest $35 billion in
data centers in Virginia. The largest private investment in the state’s
history. With that investment Amazon will take control of the grid without any
planning and has apparently also captured the VA DEQ.
DEQ Notice of action: The Department of Environmental
Quality (DEQ) is considering the issuance of an order and local variance for
data centers located in the Counties of Fairfax, Loudoun, and Prince
William. A variance is an exception to a general rule. This notice is
given in accordance with the requirements of § 10.1-1307 C of the Code of
Virginia.
Regulations affected: The primary regulation affected
by this action is 9VAC5-80-1110 C of 9VAC5-80 (Permits for Stationary
Sources).
Purpose of notice: DEQ is seeking comments on the
proposed variance.
Public comment period: January 26 to March 14,
2023 at this link
Public hearing: Conference Room, Northern Regional
Office, 13901 Crown Court, Woodbridge VA, at 11:00 a.m., on February 27,
2023.
Good
ReplyDeleteYour blog is a breath of fresh air—thoughtful, well-organized, and packed with valuable information. The content resonates with readers, making complex topics approachable and interesting. It's clear that you put a lot of effort into your posts, and it shows. I'm always eager to see what you'll share next. Keep up the outstanding work—it's much appreciated!