This report and associated analysis were prepared for DOE to
evaluate both the current state of electrical adequacy as well as future adequacy
from the combination of announced retirements and large load growth from expansion
of industry, data centers and AI.
This report serves as DOE’s response to a Presidential
Executive Order by delivering the required uniform methodology to identify
at-risk region(s) and guide reliability interventions. The report was developed
with assistance from the Pacific Northwest National Laboratory (PNNL) and
National Renewable Energy Laboratory (NREL) using data from the North American
Electric Reliability Corporation (NERC).
The highlights relating to PJM below is excerpted from the
73 page report. They developed three separate cases for 2030. The “Plant
Closures” case assumes all announced retirements occur plus generation
additions which include NERC’s Tier 1 resources category- completed and
under-construction power generation projects, as well as those with firm-signed
and approved interconnection service or power purchase agreements. The “No
Plant Closures” case assumes no retirements plus the same additions. A
“Required Build” case further compares the impacts of retirements on perfect
capacity additions needed to return 2030 to the current system level of
reliability.
The model assumes electricity moves between subregions, when
conditions start to tighten. Each region has a certain amount of capacity
available, and the methodology determines if there is enough to meet the
demand. When regions reach a “Tight Margin Level” of 10% of capacity, i.e., if
a region’s available capacity is less than 110% of load, it will start
transferring from other regions if capacity is available.
Several utilities and financial and industry analysts
identify data centers, particularly those supporting AI workloads, as a key
driver of electricity demand growth. Multiple organizations have developed a
wide range of projections for U.S. data center electricity use through 2030 and
beyond, each using distinct methodologies based on their institutional
expertise.
These projections were used to explore reasonable boundaries
for what different parts of the economy envision for the future state of AI and
data center load growth. For the purposes of this study, rather than focusing
on any specific analysis.
Key Findings:
Plant Closures Case:
- Systemwide Failures: PJM failed reliability thresholds.
- Loss of Load Hours (LOLH): Was projected to be 430 hours/year in PJM.
- Load Shortfall Severity: Max shortfall reached as high as 43% of hourly load in PJM
- Normalized Unserved Energy: Normalized for PJM was 0.1473% (PJM), far exceeding thresholds of 0.002%.
- Extreme Events: Most regions experienced ≥3 hours of unserved load in at least one year. PJM had 1,052 hours in its worst year.
- Spatial Takeaways: Subregions in PJM met thresholds—indicating possible benefits from transmission.
No Plant Closures Case:
- Improved System Performance, but PJM still experienced shortfalls.
Regional Failures:
- PJM (was the worst failure zone) 214 hours/year average, 0.066% normalized unserved energy, 644 hours in worst year, max 36% of load lost.
Key Takeaways
The Status Quo is Unsustainable. The status quo of more
generation retirements and intermittent replacement generation is neither
consistent with winning the AI race and ensuring affordable energy for all
Americans, nor with continued grid reliability (ensuring “resource adequacy”).
Absent intervention, it is impossible for the nation’s bulk power system to
meet the AI growth requirements while maintaining a reliable power grid and
keeping energy costs low for our citizens.
Grid Growth Must Match Pace of AI Innovation. The magnitude
and speed of projected load growth cannot be met with existing approaches to
load addition and grid management. The situation necessitates a radical change
to unleash the transformative potential of innovation.
Retirements Plus Load Growth Increase Risk of Power Outages
by 100x in 2030. The retirement of firm power capacity is exacerbating the
resource adequacy problem. 104 GW of firm capacity are set for retirement by
2030. This capacity is not being replaced on a one-to-one basis and losing this
generation could lead to significant outages when weather conditions do not
accommodate wind and solar generation. In the “plant closures” scenario of this
analysis, annual loss of load hours (LOLH) increased by a factor of a hundred.
Planned Supply Falls Short, Reliability is at Risk. The 104
GW of retirements are projected to be replaced by 209 GW of new generation by
2030; however, only 22 GW would come from firm baseload generation sources all
the rest is intermittent and weather dependent and climate change is impacting
solar and wind generation. Even assuming no retirements, the model found
increased risk of outages in 2030 by a factor of 34.




No comments:
Post a Comment